1 Before boards arrive2 Inspection3 First power4 Clocks and reset5 Programming and debug6 Peripherals7 RF8 Power consumption9 Early compliance checks10 Issues and rework11 For the next spin
Project
Revision
Reviewed by
Date 1 Before boards arrive1.1 A written bring-up plan lists the order of steps, what working means for each, and the equipment each needs.Power first, then clocks and reset, then the processor, then each subsystem. 1.2 Equipment is on hand: current-limited bench supply, multimeter, a scope with enough bandwidth, a logic analyzer, and the probes and adapters to reach the board. 1.3 The debug probe and programming tools are proven on a development kit with the same processor. 1.4 Bring-up firmware is ready: a minimal image that blinks an LED, prints over serial, and tests each peripheral on its own. 1.5 Supply voltage and current limit are worked out for each input, with the limit just above the expected startup current.Too high and a short can burn a trace; too low and the board never starts. 1.6 Expected current and resistance to ground are noted for each rail, so an abnormal reading stands out. 1.7 A harness or breakout that reaches every interface is built. 1.8 A log is set up for each board serial number: measurements, issues, and rework. 6 Peripherals6.1 Each subsystem is brought up on its own, in the planned order, against a written pass criterion. 6.2 Every bus is checked with a logic analyzer and a scope: addresses, levels, and rise times with the actual pull-ups.A logic analyzer shows the protocol; only a scope shows slow edges and ringing. 6.3 Memory passes full read and write patterns across its whole range.A single location can pass with swapped or shorted address lines. 6.4 High-speed links are checked for signal quality at the receiver and error counts over long runs. 6.5 Analog inputs are checked for noise, offset, and gain against a known reference. 6.6 Every connector is exercised with the real cable or mating hardware, including hot-plug where the product allows it. 6.7 Buttons, LEDs, displays, sensors, and actuators work, with motors tested under load.